Default Milestone report

I cant find where I can generate a Milestone report for all Projects? is this achievable?
Alex
Reply With Quote
  #2  
Old February 18th, 2010, 05:18 PM
Ross Spafford's Avatar
Ross Spafford Ross Spafford is offline
UDA Technical Support
 
Join Date: Sep 2008
Posts: 191
Default

Hi Alex,

We don't currently have a milestone report, but I've added that as a feature request. As a work around I'd suggest opening the list view in the calendar and setting the only visible activity type to milestone. This should show you the information you want, and allow you to print the info (or copy it to excel).
__________________
Ross Spafford
UDA Techical Support
Quickbooks Certified Pro Advisor
MCITP: Enterprise Support Technician
Reply With Quote
  #3  
Old February 19th, 2010, 02:47 AM
Alex Alex is offline
Member
 
Join Date: Nov 2008
Location: Australia
Posts: 45
Default Milestone report

A Mile stone report at easy glance for a project manager would be advisable for overseeing how all the projects are running, on time or behind. Therefore I would suggest that milestones for all projects be kept similar. they may be inspection points or progress claim certificates. as long as your project milestones are consistent for any project.
Alex
Reply With Quote
  #4  
Old February 19th, 2010, 10:34 AM
Ross Spafford's Avatar
Ross Spafford Ross Spafford is offline
UDA Technical Support
 
Join Date: Sep 2008
Posts: 191
Default

I see the milestones used most commonly to mark draws, inspections, and 25% 50% 100% complete. I agree that using a consistent set of milestones across multiple projects makes it easier to visualize the status of each one.
__________________
Ross Spafford
UDA Techical Support
Quickbooks Certified Pro Advisor
MCITP: Enterprise Support Technician
Reply With Quote
Reply

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are EST. The time now is 06:48 AM.


UDA Partners, Certifications, and Integrated Applications
UDA Customer Assistance and Sales 1-800-700-UDA1 (8321) www.udatechnologies.com info@uda1.com United States
Copyright ©2003-2009 UDA Technologies, Inc. All Rights Reserved.
Site Terms | Privacy Policy | Copyright | About UDA | Careers | Remote Demonstrations | Contact UDA | TotalCare | ConstructionSuite 2009